County Hwy O - County Hwy I
intersection

Moorland Rd and Beloit Rd

• City of New Berlin
• construction starts Spring 2020
• pavement replacement on Moorland Rd
• signals to be upgraded
• turn lanes to be added

 

Welcome to Waukesha County Public Works'
info page for the upcoming project to improve
the intersection of Moorland Rd (CTH O) and
Beloit Rd (CTH I).

Please find regular updates on project
impacts to residents, businesses, and
Waukesha County drivers. Thank you!

Questions and comments? Contact us!
Bruce Barnes, PE, PTOE (email)
Project Manager
262-548-7748 

Mary B. Pyritz, PE (email)
Consultant Project Manager         
Toki and Associates, Inc.
414‐463‐2700 x104 

O and I intersection project location

map of project location


Project Updates

October 9, 2020
Change to traffic pattern: starting Oct 19
• During a seven-day period, it won't be possible to make certain turns at the Moorland - Beloit intersection:
• drivers going north on Moorland Rd: no left turn to Beloit Rd westbound
• drivers going south on Moorland Rd: no left turn to Beloit Rd eastbound
• drivers going west on Beloit Rd: no left turn to Moorland Rd southbound; no proceeding through intersection
• drivers going east on Beloit Rd: no left turn to Moorland Rd northbound; no proceeding through intersection
• Through Oct 26 approx
• For reconstruction of centermost pavement area 

Click images below to view map.

••• 

August 21, 2020
Overnight closure next week: 
• Beloit Rd (CTH I) to close briefly at intersection with Moorland Rd (CTH O)
• No impact to Moorland Rd traffic
• Thursday August 27 • 9 pm - 6 am
• For concrete pour

••• 

Change to traffic pattern in Sept:

• Two-way traffic lanes on Moorland Rd (CTH O) to move over to the east side of the roadway
• Starting Tuesday September 1 • 9 am
• For construction of lanes on west side of roadway
• Watch for new signage, new traffic pattern

Project completion date (approx):

• Please expect to enjoy your new O and I intersection in November 2020

•••

July 24, 2020
Park & Ride to re-open: 
• Valley View Park & Ride at I-43 & Moorland Rd is set to re-open on Tuesday August 11, 2020.

•••

May 20, 2020
New public info: 
• In lieu of our usual Public Information Meeting, a mailer with project details and contact info has now been sent to residences and businesses along the project route. We look forward to resuming our gatherings with our customers as soon as possible. For now, we welcome your feedback by phone and email! 
Do your daily commutes pass through the O and I intersection? Then click "Public Info Materials" above to view this mailer, too!

•••

April 8, 2020
Temporary closure: 
• Valley View Park & Ride at I-43 & Moorland Rd to close April 17, 2020 - June 17, 2020.
Important: Vehicles not removed by April 17, 2020, will be ticketed and towed at the owners’ expense. 
• Click for more info

•••

April 6, 2020
Construction update: 
• Construction began Monday, March 30. Temporary traffic signals are now being installed at intersection of County Hwy O and County Hwy I.
Coming soon to County Hwy O
• Removal of median near County Hwy I
• Temporary closure of one northbound, one southbound lane.
•••



"Who Maintains My Road?" • Our Divisions • Contact Us • Join Our Team • return to DPW home

Waukesha County Department of Public Works
515 W Moreland Blvd  AC220 • Waukesha WI 53188
phone 262-548-7740 • fax 262-896-8097 
www.WaukeshaCounty.gov/DPW

Follow @WaukeshaCoDPW on Twitter